Schedule & Progress
This is where you can find out what is happening on site
Schedule for this month: 1st to 31st July 2010
- Continuation of Metsec metal framing
- Window installation to commence
- Copper facade to commence
Progress for last month: 1st to 30th June 2010
- Block A: Decant and demolition completed
- Block B: Structural opening commenced
- Block C: Concrete decks poured 2nd, 3rd and roof
- Block C: Electrical systems commenced in basement
- Block C: Mechanical systems commenced in basement
- Block C: Metsec framing commenced
- Block C: Basement and screed ccompleted
The Soakaway
New Building
- Creation of the permanent 'Soakaway' *
* The soakaway acts as a flood defence that captures rainwater falling in the playground or on the new building. This is then drained into what is known as attenuation cells (see picture for approx image of what they look like). These allow the surface water to be stored in one location which is then gradually released back into the ground. It is also known as a Sustainable Urban Drainage System (SUDS).