This is the place where you can have an overview of what is happening on site.

Schedule for this month: 1st to 31st of August 2010

Phase 1 - New Build

  • New build (Block D) has been handed over to the school 
  • Decanting process on new build has commenced
  • Refurb works to Blocks B&C have started
  • External works are in progress


Progress for last month: 1st to 31st of July 2010

      Phase 1 - New Build

STG New Build block D is near completion, with the building being handed over at the end of July 2010.

  • The facade works and link bridge installation is complete
  •  Internal works are complete
  •  The roof will be covered with play surface during July 2010
  •  The M&E works are complete. Testing and commissioning is well under way
  • External works drainage and surface water is near completion. Thames water will do the final connection.


 

News
Jobs
Tenders
General Internal Fit-out (all trades)

General

Apply now

Landscaping

General

Apply now

Sports pitches

General

Apply now

Drylining

Architectural trades

Apply now

Metalwork

Architectural trades

Apply now

Rendering

Architectural trades

Apply now

Cladding (curtain walling, brickwork)

Architectural trades

Apply now

Vinyl & Timber flooring

Architectural trades

Apply now

False Ceilings

Architectural trades

Apply now

Ironmongery

Architectural trades

Apply now

Mirrors

Architectural trades

Apply now

M Cubicles & Vanity tops

Architectural trades

Apply now

Painting

Architectural trades

Apply now

Lifts

Mechanical & Electrical

Apply now

Heating & Plumbing

Mechanical & Electrical

Apply now

Electrics

Mechanical & Electrical

Apply now

Fire Alarm

Mechanical & Electrical

Apply now

CCTV/Security

Mechanical & Electrical

Apply now

Air Conditioning & Ventilation

Mechanical & Electrical

Apply now