Schedule & Progress
This is the place where you can have an overview of what is happening on site.
Schedule for this month: 1st to 31st August 2010
- Preparation of handover on Block A&C
- Decanting back to Block A&C
- Facade finishing
- Testing & commissioning
- External work on the North and East playground
- Remodel temporary cabin and decant from Block B
- Demolition and refurbishment of the North part of Block B
Progress for last month: 1st to 31st July 2010
- Decanting of Block B and temporary cabin
- Progress on partitioning of Block A & C - completed
- Progress on enclosure of Block A & C - completed
- M&E second fix ongoing - completed