Schedule & Progress
This is the place where you can have an overview of what is happening on site.
Schedule for this month: 1st to 31st July 2010
Progress
- Ground floor walls complete
- 1st floor slab ongoing
- 1st floor walls commenced
- Staircase installed up to 1st floor level
Progress for last month: 1st to 31st July 2010
Overall Progress
- Strip footings / excavation complete
- Lift pit base and structure complete
- Hydrotherapy pool structure complete
- Underground drainage complete
- Below ground waterproofing complete
- Ground floor slab complete
- Ground floor walls commenced
- First floor slab commenced