Schedule & Progress

This is the place where you can have an overview of what is happening on site.

Schedule for this month: 1st to 31st July 2010

Progress

  • Ground floor walls complete
  • 1st floor slab ongoing
  • 1st floor walls commenced
  • Staircase installed up to 1st floor level

 

Progress for last month: 1st to 31st July 2010

Overall Progress

  • Strip footings / excavation complete 
  • Lift pit base and structure complete 
  • Hydrotherapy pool structure complete
  • Underground drainage complete
  • Below ground waterproofing complete
  • Ground floor slab complete
  • Ground floor walls commenced
  • First floor slab commenced

Letter to neighbours of Queen Elizabeth II Jubilee School

10th December

Subject: Introduction to the BSF project

News
Jobs
Tenders
Design Co-Ordinators

Cadre/Prin - 24/01/2008

More Info

Mechanical & Electrical Manager

CdG - 25/01/2008

More Info

Engineers

Cadre - 25/01/2008

More Info

External works Management

Prin/CdG - 25/01/2008

More Info

Management Accountant

Princ - 25/01/2008

More Info

Junior QS

Junior QS - 25/01/2008

More Info